Release 2.1.1 is the bug fix release for the failed 2.1 release. It was released on 15th November, 2007.
This listing includes all reports that have been closed within this release.
Contents |
[edit]
1 Summary
| TOTAL REPORTS | 54 |
| DUPLICATES | 2 |
| FEATURE REQUESTS ADDED (also see What's New - 2.1.1) | 3 |
| NO FAULT FOUND | 6 |
| RESOLVED | 43 |
| WON'T FIX / CHANGE | |
| ADD ON MODULES |
[edit]
2 Duplicates
| 2184 | Help! I've forgotten my password link - email incomplete |
| 2229 | Problem in Gant Charts with Greek Language |
[edit]
3 Feature Requests Added
| 2217 | No Events tab on the Project Summary display |
| 2209 | Organise Tasks > Select All |
| 2208 | Company Details Screen - doesn't include Company Owner |
[edit]
4 No Fault Found
| 2179 | Task edition - user assignement failed |
| 2203 | Forum - Editing / Deleting a created forum |
| 2222 | Tasks >> Tasks per User |
| 2227 | Project collapse behavior |
| 2237 | wrong table name in query for the reports |
| 2220 | Copying / Moving Tasks - Losing Relationships / Dependencies but keeping "settings" |
[edit]
5 Resolved
| 2177 | Report for allocated user hours failed |
| 2178 | Unassigned user from task doesn't work |
| 2181 | Project view permission are notapplied in companies active project tab |
| 2200 | Multi-Line Selection boxes are not expanded in the dotProject Classic Theme |
| 2185 | Task Log editing - original user is overwritten |
| 2190 | Task Assignment Announcement Emails - no subject included |
| 2212 | Gantt Chart not appearing with a combination of x tasks and browser width |
| 2198 | User Preferences > Task Log Emai Recording - Spelling mistake |
| 2197 | Personal Preferences - Event Filter option not honoured |
| 2182 | dPsessionDestroy function not behaving properly |
| 2221 | Adding log record with "Email Log to" checkboxes checked causes error |
| 2211 | Today Option not remembering last tab |
| 2207 | Task Listings - Overdue Flag on clear finish dates |
| 2228 | Clicking on any sortable column in tasks tab of project view page takes you to project listing page |
| 2195 | Calendar Events - Inviting Resources |
| 2204 | Files Module > Creating Multiple Versions not honouring folders |
| 2186 | To Do / Today View - Minor UI Inconsistency |
| 2180 | Moving task with children |
| 2236 | Bare LF in mail |
| 2188 | Empty Dates - incorporation of tasks on Todo and Today Views inconsistent |
| 2202 | Back from editing a forum post goes too far back |
| 2234 | File Check Out Message when running in php safe mode |
| 2226 | Slackware 12, php 5.2.4, jpgraph 2.2: greek characters on gantt charts. |
| 2189 | To Do Listing Empty Dates Option - switch between My Tasks and My Gantt |
| 2210 | Project View > Files Tab > Move to (All Projects) is misleading wording |
| 2201 | Help Link (the lifesaver image) needs to be dropped |
| 2235 | With ADD ON Module Help Desk enabled - file uploads fail silently |
| 2183 | Myinfo link is not accessible to a standard user. |
| 2065 | [SECURITY] Users cannot access to "My info" |
| 2193 | Tasks that don't relate / the current user aren't assigned to are being listed in the summary |
| 2231 | Tasks Per User > Unassign User from task |
| 2199 | Todo > My Gantt > not showing assigned tasks |
| 2191 | My Tasks To Do > Gantt Chart > Dynamic Tasks > Child Tasks not listed |
| 2187 | Error in display of "no dates" on Gantt Chart |
| 2196 | Emailing Project / Task Contacts |
| 2232 | New company creation requires Description field |
| 2192 | Log option disappears from Project task list |
| 2194 | Task end hour reset in task log |
| 2238 | Classic dotProject Theme > Project Listing > Gantt Chart |
| 2216 | [history] "show all" select not working |
| 2240 | "Blind" file x task association |
| 2215 | Texts not affected by translations packs |
| 2214 | Calculate Finish Date |
[edit]
6 Won't Fix / Change
[edit]
7 Add On Modules
[edit]
8 Return to...
[edit]